Retrofit Drawings for Burbank Soft-Story Buildings Are Due January 11, 2027
Burbank’s City Council adopted a mandatory soft-story retrofit ordinance on December 10, 2024, and its deadlines run from January 10, 2025. If your building received an Order to Comply, the screening deadline has already passed and the next one is close: engineered retrofit plans have to reach Burbank Building and Safety by January 11, 2027. YD Group engineers the retrofit, takes it through plan check and builds it, so one firm carries the building from the screening result to the final inspection.
Which Burbank Buildings the Ordinance Covers
The ordinance (No. 24-4,021, in Title 9 of the Burbank Municipal Code) applies to wood-frame, multi-story residential buildings designed under building codes in effect before January 1, 1978 that have a soft, weak or open-front wall line at the ground floor. In practice that usually means apartments or condominiums over tuck-under parking, or units above wide garage openings. Single-family homes and duplexes (Occupancy Group R-3) are exempt. The City preliminarily identified about 675 buildings.
The definitions are engineering definitions. A soft wall line has less than 70 percent of the stiffness of the wall above it, and a weak wall line has less than 80 percent of its strength. Whether a building is actually in scope is settled by the screening form and, where the City’s list is wrong, by an engineering assessment report. Buildings retrofitted under Burbank’s earlier voluntary program can be exempted when the permit records are submitted.
Every Burbank Deadline, From Screening to Final
January 12, 2026: screening form. The form goes to Building and Safety and the Notice of Order is posted at the building. This date has passed. If it was missed, the fix is to file now and move straight into the engineering.
January 11, 2027: retrofit drawings. Engineered plans and calculations submitted for plan check.
January 10, 2028: plans approved. Plan check has to be complete. A Burbank plan check stays valid for 180 days after the application date unless it is extended, so corrections cannot sit for months.
January 10, 2029: permit issued and work started.
January 10, 2030: construction complete and the permit finaled.
Burbank does not sort buildings into priority tiers the way Los Angeles does. Every covered building runs on the same five dates. The City can grant extensions of up to 180 days at a time when an owner shows a good-faith effort and a proposed schedule. Missing a deadline puts the building in violation, and the ordinance lets the Building Official record that violation against the property with the County Recorder.
Owner
Hires a California-licensed engineer and keeps the building on schedule for each of the five dates.
Engineer of Record
Submits the permit application, plans and calculations through the City’s ProjectDox system and answers every plan check comment.
Licensed Contractor
Only a contractor with a California A or B license can pull the seismic retrofit permit, start the work and call for inspections.
What the Retrofit Usually Involves
The ordinance sets the engineering standard. The retrofit has to meet the current building code as modified by the ordinance, with design forces of at least 75 percent of the code’s design base shear. Appendix A4 of the California Existing Building Code is allowed as an alternative when the whole story is analyzed. On a typical tuck-under building, that translates into steel moment frames across the parking openings, plywood shear walls where there is enough solid wall, new footings or grade beams under the new frames, and connections that tie the floor above to the new structure.
Tenants can usually stay in place. Expect noise, dust and some parking stalls out of service while the frames go in. Choosing between steel and plywood is where most of the cost is decided, and over-specifying steel is the most common way a retrofit ends up costing more than the building required.
The Permit Fee Refund That Is Still Available
Burbank refunds building permit fees for early compliance. The 100 percent refund was for owners who fully complied by July 10, 2026, and that window has closed. A 50 percent refund remains for owners who fully comply by January 10, 2028, two years ahead of the final construction deadline. The City’s roadmap ties the refund to full compliance, so confirm with Building and Safety how it measures that date before you build a schedule around the refund.
How We Handle a Burbank Retrofit
Screening and assessment. We review the Order to Comply, visit the building and confirm whether it is actually in scope. Where the City’s list is wrong, an engineering assessment report is the route to an exemption.
Design. We design the lightest scheme that meets the ordinance, whether that is steel moment frames, plywood shear walls or a mix of the two.
Plan check. The engineer of record submits through ProjectDox and turns corrections around quickly, because a Burbank plan check expires 180 days after the application date unless extended.
Construction and final. Our construction team builds the retrofit, coordinates the City inspections and closes out the permit. Because engineering and construction sit in the same office, the set that goes through plan check is the set we build.
Own buildings in the City of Los Angeles as well? That program runs on a different clock, with deadlines counted from each building’s Order to Comply, and our guide to the Los Angeles soft-story retrofit program explains it. Our soft-story retrofit service covers both cities, and single-family houses that need bolting and bracing are covered in our guide to seismic retrofitting. The City’s own soft-story page has the screening form.
Frequently Asked Questions (FAQ)
-
Is my Burbank building covered by the soft-story ordinance?
It is covered if it is a wood-frame, multi-story residential building designed under codes in effect before January 1, 1978, with a soft, weak or open-front wall line at the ground floor. Single-family homes and duplexes are exempt. The screening form, and an engineering assessment where needed, settles the question. -
When are soft-story retrofit plans due in Burbank?
January 11, 2027. The plans have to be approved by January 10, 2028, the permit issued and work started by January 10, 2029, and construction finished by January 10, 2030. -
I missed the January 12, 2026 screening deadline. What now?
File the screening form now and start the engineering. The ordinance treats a missed deadline as a violation that can be recorded against the property, so catching up quickly matters more than the date that was missed. -
Who can pull a soft-story retrofit permit in Burbank?
Only a contractor holding a California A or B license. The engineer of record submits the plans and calculations, and the licensed contractor pulls the permit and calls for inspections. -
Is there a financial incentive for retrofitting early?
Yes. Burbank refunds 50 percent of building permit fees for owners who fully comply by January 10, 2028. The 100 percent refund, for compliance by July 10, 2026, has expired. -
Does the Burbank ordinance work like the Los Angeles program?
The engineering is similar and the schedule is not. Los Angeles counts its deadlines from each building’s Order to Comply and works through priority tiers. Burbank uses one set of fixed dates for every covered building.
Get the Drawings In Before January 11, 2027
Send us the Order to Comply or the building address. We’ll confirm whether the building is in scope, what the retrofit is likely to involve, and how the work fits the deadlines that are left.